Back on the 7th of March 2024, the 8km section of Greenway from Midleton to Mogeely opened and it has proved to be very popular with walkers and runners. According to some sources, the remaining 15km section from Mogeely to Youghal is supposed to open by the end of the 2024.
I've checked the remaining section out over the last few weeks and large parts of it are complete with a nice tarmac surface. The image below shows the section east of Killeagh.
Other sections in the village of Killeagh and in Youghal still need quite a lot of work to finish. When I passed during the working week, there was no obvious sign that any major work was ongoing.
We'll have to wait and see but I wouldn't be surprised if it slips into 2025 before it opens.
Video... DRONEHAWK posted a video of the section from Youghal to Mogeely on their YouTube channel and it shows what the line looks like as of June 2024.
I have no doubt that once it opens, the section from Youghal to Killeagh will prove to be very popular with walkers, runners and visitors.